This article originally appeared in Latitude Media.

The data center boom has added a whole new layer of complexity to the already tricky work of building transmission, according to Evan Vaughan, executive director of MAREC Action, a nonprofit representing clean energy and storage interests in PJM. 

“When it comes to transmission planning, the rise of new large loads does create a challenge in terms of planning efficiency,” he explained. 

Already, PJM assigns network upgrade costs to the developers looking to connect new generation to the grid. But duplicating that process for new transmission would be an experiment. 

The risk, Vaughan said, is that if the ratepayer protection pledge isn’t integrated with robust, proactive planning frameworks (like FERC Order 1920) it will result in an inefficient, fractured, and ultimately more expensive build-out of the transmission grid. Data centers, if forced to bring their own generation and simultaneously pay for their own network upgrades and transmission build outs, wouldn’t have much incentive to move away from existing data center hotspots, causing further congestion and increasingly expensive network upgrades, he added.

(…)

This leaves PJM in a bit of a Catch-22 with regards to building new transmission, Vaughan explained. “Transmission buildout is going to be challenging just because of the aversion to investment right now, because [electricity] bills are high,” he said. But assigning costs wholly to data centers risks causing even more delays, given the lack of regulatory clarity, right when the country needs more grid infrastructure than ever.